To put things into a perspective, the mentioned deal accounts for around 12.7% of the consolidated 2018 sales.
Dalekovod published a document stating that the Swedish electric power transmission company Svenska Kraftnät, informed that the offer made by Dalekovod was chosen as the best one according to the criteria of the tender for the construction of a new 400 kV transmission line Snösätra – Ekudden.
The project includes deconstruction of existing 220 kV line, and construction of 400 kV line in the corridor of the existing one, between substations Snösätra in Stockholm and Ekudden in Huddinge Municipality.
The value of construction works is more than EUR 21m, which should be realized by 2021. To put things into a perspective, the mentioned deal accounts for around 12.7% of the consolidated 2018 sales.